Dismantling cold storage panels, Asset recovery of plant rooms, Mezzanine floor removals, Clearance
Return to empty warehouse from a 50,000 sq/ft Cold storage and Food production facility that has ceased trading. 9000m2 of Kingspan Insulated panels, 700m2 of industrial mezzanine floors, 300m2 of Offices, WC, Shower facilities for removal.
Gtek Ltd & Seagro & Arcadis
July 2020
Park Royal, NW London
C.£150,000
6 week programme, technically challenging to reduce waste and maximise the re-use of modern insulation PIR panelling. Working at heights of 12m to be managed effectively and safely.
Completed on programme.
2 external client safety audits achieving over 95%.